WORKS EXECUTED/BEING EXECUTED WITH ALLOCATION OF PLAN SCHEME
" STRENGTHENING OF INFRASTRUCTURE"DURING 2007-08.
|
S.No. |
Name of work |
Estimated cost |
Remarks |
|
1. |
2. |
3. |
4 |
|
1 |
Repairs of Ghats and retailing wall of pond at village Khuda Jassu. |
Rs. 2,73,000
|
Work completed |
|
2. |
Concretization of left out streets at village Sarangpur, U.T., Chandigarh. |
Rs. 4,33,000
|
Work completed |
|
3. |
Revised estimate for cement concrete paving and conversion of surface drains into underground system by laying R.C.C. pipes in all streets at village Khuda Jassu, U.T., Chandigarh. |
Rs. 28,23,000
|
Work completed |
|
4. |
Development of park on the existing pond site at village Daria, U.T., Chandigarh |
Rs. 99.000
|
Work completed |
|
5. |
Repair/Renovation of Lav. Block at village Raipur Khurd, U.T., Chandigarh. |
Rs. 96,000
|
Work completed |
|
6. |
Laying of R.C.C. storm water drainage line for the disposal of waste water at village Kishangarh, U.T., Chandigarh. |
Rs. 4,71,000
|
Work completed |
|
7. |
Construction of Boundary wall of panchayat land at village Khuda Alisher, U.T., Chandigarh. |
Rs. 1,80,000
|
Work completed |
|
8. |
Laying of R.C.C. storm water drainage line for the disposal of waste water of streets at village Behlana, U.T., Chandigarh. |
Rs. 14,19,000
|
Work completed |
|
9. |
Laying of R.C.C. storm water drainage line for the disposal of waste water of streets at village Khuda Lahora, U.T., Chandigarh. |
Rs. 10,70,000
|
Work completed |
|
10. |
Renovation of Lavatory Block at village Khuda Jassu, U.T., Chandigarh. |
Rs. 3,05,000
|
Completed |
|
11. |
Concretization of path approaching to cremation ground at village Sarangpur, U.T., Chandigarh. |
Rs. 4,71,000
|
Completed |
|
12. |
Construction of boundary wall of cremation ground at village Sarangpur, U.T., Chandigarh. |
Rs 5,21,000
|
Completed |
| |
Works in progress |
|
|
|
13. |
Filling of pond in S.C. locality at village Khuda Alisher, U.T., Chandigarh. |
Rs. 11,14,000
|
In progress |
|
14. |
Conversion of surface drains into underground system by laying of RCC pipes in all streets at village Sarangpur, U.T. Chandigarh. |
Rs. 77,96,000
|
In progress |
|
15. |
Conversion of surface drains into underground system by laying of RCC pipes in all streets at village Kishangarh, U.T., Chandigarh. |
Rs. 25,86,000
|
In progress |
|
16. |
Renovation of Lavatory Blocks at village Behlana, U.T., Chandigarh. |
Rs. 6,11,000
|
In progress |
|
Works to be taken up |
|
17. |
Repair/renovation of Lavatory Block at village Sarangpur, U.T., Chandigarh. |
Rs. 3,46,000
|
Work to be taken up. |
|
18. |
Repair/renovation of Lavatory Block at village Daria, U.T., Chandigarh. |
Rs. 3,46,000
|
Work to be taken up. |
|
19. |
Repair/renovation of Lav. Block at village Makhanmajra, U.T., Chandigarh. |
Rs. 3,46,000
|
Work to be taken up. |
|
20. |
Cleanliness and sanitation in villages. |
Rs 40,00,000
|
|
|
21. |
Installation of solar lights in all U.T. villages |
Rs 40,77,000
|
|
|
22. |
Renovation of Panchayat building of Sarangpur & Mauli Jagran for starting rural poly-clinics |
Rs 28,48,000 |
|
|
23. |
Infrastructure facilities to Zila Parishad |
Rs 4,00,000
|
|
|
24. |
Infrastructure facilities to Panchayat Samiti |
Rs 18,00,000
|
|
| |
Total |
Rs 3,44,31,000
|
|
PROPOSED UTILISATION OF ALLOCATION OF Rs.500.00 LAKH ANNUAL PLAN 2008-09
(Rs. In lakhs)
|
S.No. |
Item of which expenditure proposed to be incurred during 2008-09 |
Anticipated Expenditure
|
|
1. |
2. |
3. |
|
1. |
Infrastructure facilities to Zila Parishad |
7.00 |
|
2. |
Infrastructure facilities to Panchayat Samiti |
18.00 |
|
3. |
Sanitation and Cleanliness in U.T. villages. |
50.00 |
|
4. |
Execution of works like |
|
| |
(i)Additional renovation in poly clinic of village Mauli Jagran |
15.00 |
| |
(ii)Construction of sports stadium Kaimbwala |
60.00 |
| |
(iii)Construction of surface drains into underground system by laying RCC pipe in village Makhanmajra |
50.00 |
| |
(iv) Construction of Janj Ghar in village Makhanmajra |
54.19 |
| |
(v) Construction RCC walls of Ganda Nallah in village Mauli Jagran AND
Construction of bridge on the Ganda Nallah in village Mauli Jagran
|
205.81
|
| |
(vi) Additional Funds required for sports complex Kaimbwala in view of new design with more sports facilities.
|
40.00
|
| |
Total |
500.00
|
|
 |